San Jose Solar Pump Irrigation Project

Drilling Works and Construction of Solar Pump Facilities

Location: 
Tuy, Batangas
Approved Budget for the Contract: 
₱7,124,698.05
Winning Contractor: 
D'brothers International Trading Corporation
Detailed Estimates as Awarded: 
Start of Construction: 
March 30, 2023
Target Date of Completion: 
October 23, 2023
Completion Rate: 
90.54%
Project Status: 
On-going
Implementing Office: 
Cavite-Batangas Irrigation management Office
Responsible Official: 
Engr. Romulo M. Angeles
Designation: 
Acting Division Manager
Responsible Official Contact: 
(046) 412-0282
Electronic Mail Address: 
r4a.cavitebatangas-imo@nia.gov.ph
Detailed Actual Cost of the Project: 
₱7,116,659.08