Papaya Pump Irrigation Project

Construction of Solar Pump Facilities

Location: 
Tingloy, Batangas
Approved Budget for the Contract: 
₱6,536,516.61
Winning Contractor: 
TTAI Gen. Construction
Detailed Estimates as Awarded: 
Start of Construction: 
April 26, 2023
Target Date of Completion: 
November 20, 2023
Completion Rate: 
100.00%
Project Status: 
Completed
Source of Fund: 
EGPIP
Implementing Office: 
Cavite-Batangas Irrigation management Office
Responsible Official: 
Engr. Romulo M. Angeles
Designation: 
Acting Division Manager
Responsible Official Contact: 
(046) 412-0282
Electronic Mail Address: 
r4a.cavitebatangas-imo@nia.gov.ph
Detailed Actual Cost of the Project: 
₱6,528,433.81