Embarcadero River Irrigation System

Construction of Canal Lining (Sta 0+000 - 0+078.30 MC & Sta. 2+794.00 - 2+908.00 MC)

Location: 
Dasmariñas, Cavite
Approved Budget for the Contract: 
₱2,681,554.24
Winning Contractor: 
Mechanics Cons. Corp.
Detailed Estimates as Awarded: 
Start of Construction: 
April 26, 2023
Target Date of Completion: 
August 23, 2023
Completion Rate: 
100.00%
Project Status: 
Completed
Source of Fund: 
RRNIS
Implementing Office: 
Cavite-Batangas Irrigation management Office
Responsible Official: 
Engr. Romulo M. Angeles
Designation: 
Acting Division Manager
Responsible Official Contact: 
(046) 412-0282
Electronic Mail Address: 
r4a.cavitebatangas-imo@nia.gov.ph
Detailed Actual Cost of the Project: 
₱2,673,593.67